A motor grader continues to maintain construction areas to provide access for the 500-800 trucks that come in and out each day hauling dirt. In total, 6,500-10,400 cubic yards of dirt are moved each day and it is pulled from areas along Nissan Parkway on both sides of Highway 43.
A motor grader continues to maintain construction areas to provide access for the 500-800 trucks that come in and out each day hauling dirt. In total, 6,500-10,400 cubic yards of dirt are moved each day and it is pulled from areas along Nissan Parkway on both sides of Highway 43.
Construction continues on a 1.35-million square-foot supplier park for Nissan in Canton.

Groundbreaking took place in July 2013 and is expected to be completed by the end of 2014 or in the first part of 2015.

Officials anticipate 250,000 square-feet of space to be operational by July 1.